Project
Computerized Maintenance Management System (CMMS) for Bole Lemi Special Economic Zone
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
PROJECT TIMELINE TRACKING
Today Mon, July 8, 2024
48%
Overall Progress
2/5
Phases Completed
Status
1.Project Initiation
Ongoing
Duration
1 week
Stage completion
100%
Priority
High
Development Files & Documents:
Development Documentation
Testing Documentation
Key Deliverables:
-
✓ Project Charter
-
✓ Stakeholder Analysis
-
✓ Initial Risk Assessment
-
✓ Project Kick Off
-
✓ Stakeholder Meeting
-
✓ Plan Requirement Analysis
-
✓ Begin the Requirement Analysis
2.Requirements Analysis & Design
Ongoing
Duration
3 weeks
Stage completion
100%
Priority
High
Reports & Documents:
Requirement Analysis Phase Report
CMMS Requirement Analysis Document
Key Deliverables:
-
✓ Requirements Documentation
-
✓ System Architecture Design
-
✓ UI/UX Wireframes
-
✓ Technical Specifications
-
✓ Document Materials
-
✓ Other Materials
-
✓ Questionnaires
-
✓ Surveys on Requirements
3.Development
Near Completion
Duration
5 weeks
Stage completion
90%
Priority
Medium
Development Files & Documents:
Requirement Analysis Phase Report
CMMS Requirement Analysis Document
Key Deliverables:
-
🔄 Core System Development
-
✓ Database Implementation
-
✓ API Development
-
🔄 Unit & Integration Testing
-
⏳ User Acceptance Testing
4.Testing
Pending
Duration
2 weeks
Stage completion
0%
Priority
High
Key Deliverables:
-
⏳ System Testing
-
⏳ User Acceptance Testing
-
⏳ Performance Testing
-
⏳ Bug Fixes & Optimization
5.Training & User Adoption
Pending
Duration
4 weeks
Stage completion
0%
Priority
Medium
Key Deliverables:
-
⏳ Training Materials
-
⏳ User Manuals
-
⏳ Training Sessions
-
⏳ Support Documentation
6.Final Exit Report
Pending
Duration
2 weeks
Stage completion
0%
Priority
Low
Key Deliverables:
-
⏳ Project Closure Report
-
⏳ Lessons Learned Document
-
⏳ Final Presentation
-
⏳ Handover Documentation
Project Timeline Overview
6 Phases
18 Weeks
48% Complete
Phase
Timeline
Progress
Status
Project Initiation
100%
Completed
Requirements Analysis & Design
100%
Completed
Development
90%
Near Completion
Testing
0%
Pending
Training & User Adoption
0%
Pending
Final Exit Report
0%
Pending