Project
Computerized Maintenance Management System (CMMS) for Bole Lemi Special Economic Zone
Client
Deutsche Gesellschaft für Internationale Zusammenarbeit (GIZ) GmbH
PROJECT TIMELINE TRACKING
Today Mon, July 8, 2024
83%
Overall Progress
5/6
Phases Completed
In service
Live at bolelemi.et
1.Project Initiation
Completed
Duration
1 week
Stage completion
100%
Priority
High
Key Deliverables:
-
✓ Project charter
-
✓ Stakeholder analysis
-
✓ Initial risk assessment
-
✓ Project kick-off and stakeholder meeting
-
✓ Plan for the requirement analysis
2.Requirements Analysis & Design
Completed
Duration
3 months
Stage completion
100%
Priority
High
Reports & Documents:
Requirement Analysis Phase Report
CMMS Requirement Analysis Document
Key Deliverables:
-
✓ Requirements documentation, section 8 of the CMMS analysis
-
✓ System architecture design
-
✓ UI/UX wireframes
-
✓ Technical specifications
-
✓ Questionnaires and surveys on requirements
3.Development
Completed
Stage completion
100%
Priority
High
Key Deliverables:
-
✓ Work requests and work orders, from approval through close, with materials, helpers, photos, and a tenant rating
-
✓ Preventive maintenance by calendar and by meter use, with missed-work alerts
-
✓ Assets with location, map, QR label, barcode, manuals, drawings, and warranties
-
✓ Stores: request, reserve, issue, return, reorder, batch, expiry, and a purchase when the shelf is short
-
✓ Tenant portal, utility billing, water, wastewater, safety, and the report pack
-
✓ Field page with before and after photos, and staff and tenant phone apps
4.Testing
Completed
Stage completion
100%
Priority
High
Key Deliverables:
-
✓ System testing of the request, job, store, and billing path
-
✓ User acceptance with the park roles
-
✓ Fixes carried into the live service
5.Training & User Adoption
Completed
Stage completion
100%
Priority
High
Key Deliverables:
-
✓ A manual for the tenant, technician, supervisor, accounts, store, and administrator
-
✓ Trainer guides, in English and Amharic for the floor and the counter
-
✓ Each person lands on their own work: field jobs, billing, stock, or incoming requests
6.Final Exit Report
Empty
Duration
2 weeks
Stage completion
0%
Priority
Low
Project Timeline Overview
6 Phases
5 Completed
83% Complete
Phase
Timeline
Progress
Status
Project Initiation
100%
Completed
Requirements Analysis & Design
100%
Completed
Development
100%
Completed
Testing
100%
Completed
Training & User Adoption
100%
Completed
Final Exit Report
0%
Empty